Construction of HDPE-lined containment area with foundations for new surge and sludge tanks. Installation of underground water and sewer lines and relocation of existing effluent piping.

Construction of foundations for new waste water treatment equipment and pipe rack. Construction of a new deep well; the  deep well was cast in place and sunk to the correct elevation with a hydro-vac truck due to lack of room for excavation in an active refinery and the existing active waste water treatment API in close proximity. Installation of underground piping to the deep well, piping inside the well and extending of existing force main.

Client Company:Husky Oil Operations
Location:Prince George, BC
Start date:June 2011
project status:Completedend date:March 2012