Careers Call Us: 1-250-649-0561

Arctic Construction Ltd. – Yukon Zinc Concrete Supply and Civil Work

Produce, deliver, and pump 9,000m3 of concrete for the foundations and slabs for Yukon Zinc Mine project. The concrete was supplied from June through December; 4,000m3 were poured from November through December 18th. Our largest single pour was 535m3. We were producing 60m3 per hour on-site. We have four 8m3 concrete mixers and a 36m boom pump.

 

Project also included the supply and install of formwork and reinforcing steel for the concrete foundation for two new mine buildings, concentrate load-out building and mill building approximately 3,000m2.

Client Company:

Arctic Construction Ltd.

Location:

Robert Campbell Highway, km 193, Yukon

Completion Date:

December 2009

Your Vision + Our Team = SUCCESS

Contact us