Yukon Zinc Concrete Supply and Civil Work
Produce, deliver, and pump 9,000 cubic meters of concrete for the foundations and slabs for Yukon Zinc Mine project. The concrete was supplied from June through December; 4000 cubic meters were poured from November through December 18th. Our largest single pour was 535 cubic meters. We were producing 60 cubic meters per hour on site. We have 4 8m3 concrete mixers and a 36 meter boom pump.
Project also included the supply and install of formwork and reinforcing steel for the concrete foundation for two new mine buildings, concentrate load-out building and mill building approximately 3,000m2
Client Company:
Arctic Construction Ltd.
Location:
Robert Campbell Highway, km 193, Yukon
Completion Date:
December 2009